Fossil completes commissioning of Unit 60 BMS Upgrade Project at the Consolidated Edison, East River Station

Commissioning has been successfully completed for the Unit 60 BMS at the Consolidated Edison East River Station. This project included the design, supply, and commissioning of the BMS, field mounted operator interface panels, main flame scanners, natural gas ignitors, fuel safety shut-off valves, and a duplex blower. In addition, the BMS controls were interfaced with the boiler’s OvationTM system.