  March 29, 2002

Fossil Power Systems Inc. is pleased to announce the successful commissioning and startup of BC Hydro's Burrard GS Unit 6.


Fossil completed a "migration" of the original Bailey INFI90 BMS using Foxboro's migration FBM platform.

Fossil was responsible for the design and commissioning of the BMS and operator interface. This is the first of six units to be completed in the next sixteen months. Three of the units will also include the supply of Spectrum VIR flame scanners and cooling air blowers.