Fossil completes gas conversion and BMS upgrade of an auxiliary boiler at the NRG Middletown Power Station.
Fossil has successfully completed a gas conversion for an auxiliary boiler as part of a BMS upgrade at the NRG Middletown Power station in Middletown, Connecticut. The project included the design, supply and commissioning of a Siemens Procidia based BMS and operator interface, as well as a natural gas valve train.