June 1, 2001 - Fossil
Power Systems Inc. is pleased to announce the successful commissioning
and startup of Ontario Power Generations Lakeview GS
Units 1 and 2. The controls and burners were upgraded on the two
300MW coal-fired boilers as part of the low-NOx upgrade at the
plant.
Fossil completed the design, manufacturing, supply
and commissioning of the BMS, flame scanners, oil ignitors and
operator interface. The BMS was designed and implemented using
the Siemens/Moore APACS platform. The operator interface was developed
using Fossils Graphical Control System (GCS), a Windows2000-based
open architecture DCS software.
|
|